MEPCO New Connection Processing Time – What to Expect

MEPCO New Connection Timeline Overview

Getting a new MEPCO electricity connection involves multiple stages. Understanding the timeline helps you plan and follow up effectively if there are delays.

Stage-by-Stage Processing Time

Stage 1: Application Submission

Submit application at Sub-Division office. Immediate — same day.

Stage 2: Site Survey

MEPCO team visits to assess your location and determine cable route and costs. Typically 3–7 working days after application.

Stage 3: Demand Notice Issuance

After survey, MEPCO calculates charges and issues demand notice. Typically 3–5 working days after survey.

Stage 4: Payment Processing

You pay the demand notice amount. Next working day after payment is confirmed.

Stage 5: Material Procurement and Work Order

MEPCO procures materials (cable, meter) if not in stock. Can take 3–15 working days depending on stock availability.

Stage 6: Installation

MEPCO installs meter and service connection. 1–2 working days for the actual work once materials are ready.

Estimated Total Time

  • Best case (material in stock): 15–21 working days
  • Typical case: 21–40 working days
  • Complex cases (new pole needed): 45–90 days
  • Agricultural connections: 60–120 days

What Can Cause Delays?

  • Material shortage (cables, meters) at MEPCO stores
  • High volume of pending connection applications
  • Need for new pole installation or transformer augmentation
  • Incomplete documentation from applicant
  • Right-of-way issues for cable installation
  • Weather (heavy rain delaying outdoor work)

How to Follow Up on a Delayed Connection

  1. Call 118 with your application number
  2. Visit your Sub-Division office and speak to the SDO (Sub-Division Officer)
  3. If delayed beyond committed timeframe, file complaint at CCMS portal
  4. Escalate to NEPRA if Sub-Division is unresponsive

Frequently Asked Questions (FAQ)

Q: What is MEPCO's official commitment for new connection time?

A: MEPCO is required under NEPRA regulations to provide new domestic connections within a specified number of days after payment of demand notice. Check the current NEPRA service quality standards for exact timeframes.

Q: Can I speed up my MEPCO connection?

A: Follow up regularly at the Sub-Division office. Ensure all documents are complete and payment is confirmed. For urgent business needs, escalate to the Division Manager with a written request.

Q: What if MEPCO misses the promised connection date?

A: File a formal complaint through CCMS and escalate to NEPRA. MEPCO is held accountable to service quality standards set by NEPRA.